Regional record
What the NPP delivered in Ashanti
Regional capital: Kumasi
3,351
Projects
2,625
Completed (78%)
14
Sectors active
Sector performance
Completion rate and project count by sector.
77%
Education
1,180 projects
914 completed
83%
Water, Works And Housing
696 projects
576 completed
94%
Digitalisation
396 projects
373 completed
66%
Roads And Transport
356 projects
234 completed
67%
Health
246 projects
166 completed
69%
Trade And Industry
134 projects
92 completed
75%
Security
92 projects
69 completed
85%
Energy
82 projects
70 completed
Projects over time
Projects by sector
3,351
Projects
- Education35%
- Water, Works And Housing21%
- Digitalisation12%
- Roads And Transport11%
- Health7%
- Trade And Industry4%
- Others10%
% completed
<4040+60+80+
Bubbles are districts (sized by project count). Dots are GPS-located projects — click to open.
National programmes here
Flagship national initiatives delivered in this area.
Flagship projects here
View all 3,351
Water, Works And HousingCompletedKumasi Road and Drainage Extension Project (KRDEP)
Asokwa Municipal, Ashanti
Completed 2021Road Infrastructure
Roads And TransportNot CompletedUpgrading of Dampayaw-Tutuka Road
Akrofuom District, Ashanti
40% complete
40% completeRoad Infrastructure
EducationNot CompletedEstablishment of New Creative Arts Senior High School at Kwadaso
Kwadaso Municipal, Ashanti
54% complete
54% completeEducation
Roads And TransportNot CompletedRehabilitation, Upgrading Of Selected Roads In Ejisu Municipality
Ejisu Municipal, Ashanti
42% complete
42% completeRoad Infrastructure
EducationCompleted
Construction of 3-Unit Classroom Block at Dompoase SHS
Adansi North District, Ashanti
CompletedEducation
Roads And TransportCompleted
Upgrading of Amantena junction - Wiawso -Senkye Road
Asante Akim North Municipal, Ashanti
Completed 2023Agriculture