District record
What the NPP delivered in Akatsi North District
Volta Region
52
Projects
30
Completed (58%)
7
Sectors active
Sector performance
Completion rate and project count by sector.
Projects over time
Projects by sector
52
Projects
- Education40%
- Water, Works And Housing15%
- Health12%
- Digitalisation10%
- Roads And Transport10%
- Trade And Industry10%
- Others4%
% completed
<4040+60+80+
Dots are GPS-located projects — click any to open.
National programmes here
Flagship national initiatives delivered in this area.
Flagship projects here
View all 52Water, Works And HousingNot Completed
Construction of 2 No.10 Seater Water Closet Toilet at Akatsi North
Akatsi North District, Volta
33% complete
33% completeGovernance
Water, Works And HousingNot Completed
Construction of Drains (1.5km) at Ave Dakpa
Akatsi North District, Volta
91% complete
91% completeGovernance
Water, Works And HousingNot CompletedConstruction of 15No. Culverts within Akatsi North
Akatsi North District, Volta
85% complete
85% completeGovernance
Water, Works And HousingNot Completed
Construction of 11No. Mechanised Boreholes within Akatsi North
Akatsi North District, Volta
65% complete
65% completeGovernance
Water, Works And HousingNot Completed
Construction of 1No. 10-Seater Water Closet Toilet with Ancillary Facilities at Ave Dakpa Market
Akatsi North District, Volta
20% complete
20% completeGovernance
HealthNot CompletedHealth Theatre
Akatsi North District, Volta
58% complete
58% completeHealth
Roads And TransportCompleted
Reshaping and Re-gravelling of Township Road (3.5km)
Akatsi North District, Volta
Completed 2022Governance
HealthCompletedConstruction of CHPS Compound at Kpeduhoe
Akatsi North District, Volta
Completed 2018Health