District record
What the NPP delivered in Tain District
Bono Region
65
Projects
57
Completed (88%)
11
Sectors active
Sector performance
Completion rate and project count by sector.
92%
Education
26 projects
24 completed
100%
Digitalisation
17 projects
17 completed
57%
Water, Works And Housing
7 projects
4 completed
100%
Health
5 projects
5 completed
100%
Food Security
2 projects
2 completed
50%
Security
2 projects
1 completed
100%
Environmental Protection
2 projects
2 completed
0%
Roads And Transport
1 projects
Projects over time
Projects by sector
65
Projects
- Education40%
- Digitalisation26%
- Water, Works And Housing11%
- Health8%
- Food Security3%
- Security3%
- Others9%
% completed
<4040+60+80+
Dots are GPS-located projects — click any to open.
National programmes here
Flagship national initiatives delivered in this area.
Flagship projects here
View all 65EducationNot Completed
2-Unit Classroom Block at Presby B/S
Tain District, Bono
80% complete
80% completeEducation
Water, Works And HousingCompletedRepairs And Maintenance Of 30No. Boreholes
Tain District, Bono
Completed 2021Water & Sanitation
Roads And TransportNot CompletedGhana Productive Safety Net Project
Tain District, Bono
43% complete
43% completeLocal Government
Water, Works And HousingCompleted1No. 1-Unit 20 Seater Aqua-Privy at Brodi
Tain District, Bono
Completed 2018Water & Sanitation
Environmental ProtectionCompleted
Ghana Productive Safety Net Project
Tain District, Bono
Completed 2022Local Government
EducationCompletedRenovation of 1No. Agric SHS Headmaster's Bungalow at Menji
Tain District, Bono
Completed 2022Education
Environmental ProtectionCompleted
Ghana Productive Safety Net Project
Tain District, Bono
Completed 2022Local Government
Water, Works And HousingCompletedRenovation of Residence for the DCE of Nsawkaw
Tain District, Bono
Completed 2022Local Government