262 projects found

Siting, drilling and mechanization of 4No. Electric powered with 5,000L capacity tank mounted on an elevated stand at Pelungu.
Nabdam District, Upper East
Water, Works And HousingNot Completed
35%
complete

Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Paga Health Centre
Kassena Nankana West District, Upper East
Water, Works And HousingNot Completed
66%
complete
10-Seater Water Closet Institutional Toilets with Mechanised Boreholes at Gbedema
Builsa South District, Upper East
Water, Works And HousingNot Completed
95%
complete
10 Seater Water Closet Toilet with Mechanized Borehole at Alhaji 44 Community
Binduri District, Upper East
Water, Works And HousingNot Completed
95%
complete

Mechanized Solar Powered Water System at Zenga
Kassena Nankana West District, Upper East
Water, Works And HousingNot Completed
40%
complete
Construction of Mechanized Solar Powered Water System at Tanga
Bawku West District, Upper East
Water, Works And HousingNot Completed
90%
complete
Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Boko Community
Binduri District, Upper East
Water, Works And HousingNot Completed
95%
complete
Construction of Mechanized Solar Powered Water System at Patilmi
Bawku Municipal, Upper East
Water, Works And HousingNot Completed
90%
complete
Drilling and Installation 37 boreholes
Bolgatanga East District, Upper East
Water, Works And HousingNot Completed
55%
complete
Siting and Drilling of 1No. Boreholes fitted with Handpumps at Yidonde
Bawku West District, Upper East
Water, Works And HousingNot Completed
70%
complete
10-Seater Water Closet Institutional Toilets with Mechanised Boreholes at Uwasi
Builsa South District, Upper East
Water, Works And HousingNot Completed
90%
complete
Construction of 1No. 10-Seater Water Closet Toilet at Bador
Bawku Municipal, Upper East
Water, Works And HousingCompleted
10-Seater Water Closet Institutional Toilets with Mechanised Boreholes at Kanjarja-Nyansa
Builsa South District, Upper East
Water, Works And HousingNot Completed
95%
complete
10 Seater Water Closet Toilet with Mechanized Borehole at Widana Community
Pusiga District, Upper East
Water, Works And HousingNot Completed
90%
complete
Sitting and drilling of 12No. Boreholes fitted with hand pumps at twelve (12) communities in the district
Nabdam District, Upper East
Water, Works And HousingNot Completed
51%
complete

Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Bazua Community
Binduri District, Upper East
Water, Works And HousingNot Completed
95%
complete
Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Zebilla Hospital
Bawku West District, Upper East
Water, Works And HousingNot Completed
39%
complete
Construction of Audit Service Office Complex
Kassena Nankana Municipal, Upper East
Water, Works And HousingNot Completed
98%
complete

Mechanized Community Water System at Zambala-Bugri
Tempane District, Upper East
Water, Works And HousingCompleted

10 Seater Water Closet Toilet with Mechanized Borehole at Mirigu SHS
Kassena Nankana West District, Upper East
Water, Works And HousingNot Completed
66%
complete

Construction of community center with a hall, store, an office and unit 2-bath and toilet each at Asonge.
Nabdam District, Upper East
Water, Works And HousingNot Completed
45%
complete
1No. Culvert at Kayinchengu
Pusiga District, Upper East
Water, Works And HousingNot Completed
40%
complete
Sitting, drilling and mechanization of 1no. Solar powered with 5,000l capacity tank on an elevated stand at logre putin
Nabdam District, Upper East
Water, Works And HousingNot Completed
36%
complete
Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Zanlerigu SHS
Nabdam District, Upper East
Water, Works And HousingNot Completed
90%
complete