Construction of 1D1F - Viride Energy Africa at Nkwanta Fetteh Kakraba
Completed Part of One District One Factory Nkwanta Fetteh Kakraba, Gomoa East District, Central Trade And Industry

About this project
Processing of billion old tyres into biofuel- Viride Energy Africa at Nkwanta Fetteh Kakraba
1 Unit
Scope
100%
Completed
Project location
Open larger map · approximateProject impact
Positive
- 1 Unit delivered
- Beneficiaries: The Ghanaian Populace
- Completed 1 Jan 2019
Evidence & sources
No public sources attached yet. This record is shown with an unverified status. Know more about this project? Tell us →
Related projects
More in Trade And Industry
Environmental ProtectionNot CompletedAnomabo Coastal Protection Project
Mfantseman Municipal, Central
80% complete
80% completeHousing & Works
Environmental ProtectionNot CompletedSea Defence Project at Cape Coast
Cape Coast Metropolitan, Central
80% complete
80% completeHousing & Works
Environmental ProtectionNot CompletedEmergency Sea Defence Project (Phase III) (Elmina)
Komenda Edina Eguafo Abirem Municipal, Central
95% complete
95% completeHousing & Works
Trade And IndustryNot Completed
Ghana CARES “ObaatanPa” Programme
Nationwide
90% complete
90% completeFinance